Image of a water butt

Action for Staveley

We’re on a mission to make the North West stronger and for Staveley that means increasing resilience towards climate change through rainwater management.

Cumbria sees its fair share of rain and Staveley is no exception. To tackle these challenges, we are improving our network to meet demands for now and in the future. As part of our Action Plan for Staveley we have developed plans to reduce storm water spills into the River Kent.

Work is underway within the wastewater treatment works and on Windermere Road. We’re pleased to report that good progress is being made. Our work on Main Street is now complete and we're now working within the playground and on Gowan Terrace.

Staveley Project Update: River Crossing

As you’re aware we’re currently carrying out a multi-million-pound infrastructure project in Staveley focused on upgrading the treatment works and increasing the size of our pipes to reduce sewer flooding and improve the water quality in the River Kent.

Part of our work involves building a new pipeline across the river. It’s been key that we’ve worked really closely with the Environment Agency to ensure our work doesn’t have a negative impact on river habitats and to obtain the necessary environmental permits. This project is complex and we submitted the application back in February. Since then, we’ve been having ongoing discussions, responded to all requests and met the required timescales to support the assessment. We have now been granted the permits needed to do the work but unfortunately this does mean there will be an impact on the timeline for reopening the playground.

We are working closely with our partners to accelerate the remaining programme wherever possible and minimise any further delay. To help achieve this, we will be working on the installation of the new pipe across the River Kent at weekends (both Saturdays and Sundays), weather permitting.

We expect work to begin on the river crossing on Wednesday 30 July and are aiming to complete this phase and hand the playground back to the Staveley Village Association by the end of September. Installation of the new playground will then commence. Pipeline works will still progress throughout the river crossing programme.

We will continue to work with the Staveley Village Association and keep the community updated on the project’s progress. If you have any questions or concerns, you can come to our drop in sessions every Tuesday at the Pavilion Building, between 2pm and 4pm, where members of the project team will be available to speak to.

  • Our work involves laying some new pipework across the River Kent, and in order to do this we need to work within the Environmental Agency time frames so as not to affect habitat in the river. To complete our work safely it is necessary to close the playground and remove some of the play equipment. The playground will be closed from Saturday 16 May.

    Noticeboards will be available on site to explain our work. 

    On completion of our work, new items of play equipment will be installed in the play area. We have liaised with Staveley Village Association and Staveley primary school prior to undertaking this work and the new play equipment has been chosen by children from the school. More than half of the Ayland playing field will remain open and access to the field will be from The Mill entrance. We apologise for the inconvenience of this closure during the summer months.

  • To undertake the installation of a new pipe in the road there will be some temporary road closures. We know road closures are inconvenient and will complete this activity as quickly and safely as possible.

    Main Street is now open and our team have moved along to carry out work within Gowan Terrace which will be temporarily closed until Monday 10 August 2026. During this time our team will work for longer periods, including weekends, to complete this section of work as quickly as they can.

     

  • During the road closure, the buses will not drive through the village along Kendal Road. They will travel into the village via the North entrance off the A591 using Windermere Road, stopping for passengers at Abbey Square bus stops opposite Staveley Village Hall.

  • Work on Windermere Road is underway and will progress across the field. Our work on Brow Lane has also started.  We'll keep residents impacted by the work updated as we progress.

  • While we're working in Staveley, we're holding a weekly community drop-in session each Tuesday, starting Tuesday 16 June at The Pavillion between 2pm and 4pm. Members of the project team will be available to answer your queries and provide updates on our programme of work.

    Please be mindful of construction traffic in the area, which will be managed by traffic marshals.

    We understand construction work can be disruptive and apologise for any inconvenience this may cause. Please be assured this work will not affect your clean or wastewater services.